Construction progress as of October 1, 2026 | Sunny Paradise
Back

Construction progress as of October 1, 2026

Installation of the ventilated façade with mineral wool insulation – 80% complete

Installation of railings on the terraces and accessible roof – 30% complete

Tiling of the accessible roof – 100% complete

Tiling of corridors and common areas – 100% complete

Tiling of the elevator shafts – 100% complete

Installation of Grilyato ceilings in the common areas – 25% complete

Installation of partition walls in the common areas – 50% complete

Installation of balcony lighting – 50% complete

Installation of light fixtures in the common areas – 20% complete

Installation of decorative decking slats on the elevator shafts – 35% complete

We’ll keep you updated on the progress. See you on site!

Construction works are progressing strictly according to schedule.


Contact us with just one click
Choose a messaging app that works for you.
We will find an apartment for you
Please fill in the required fields or try again.
Thank you! We have received your request and will contact you shortly.
✓
✕